Construction of an Integrated Fuel Station
Delivery of a complete fuel station project within the infrastructure portfolio, covering all civil and structural works and equipment to the latest technical standards.
A complete fuel station construction project within the infrastructure portfolio, delivered by Technique City from civil and structural works through to canopies and final equipment ready for operation.
The scope covered paving, the steel canopy, islands, fuel tanks, safety and firefighting systems and lighting, in full compliance with Civil Defence and the relevant authorities' requirements.
The project was completed with modern, integrated equipment to a high and reliable standard, managed to control quality and programme and hand over a station in full conformity with the technical specifications.

Civil and structural works, construction of the steel canopy, islands and paving, installation of fuel tanks, safety, firefighting and lighting systems, and final equipment through to commissioning.
- 1
Civil works
Paving, foundations, islands and civil infrastructure works.
- 2
Canopy & structure
Constructing the steel canopy and the station's structural frame.
- 3
Tanks & systems
Installing fuel tanks and the safety, firefighting and lighting systems.
- 4
Fit-out & handover
Final equipment, inspection and handover of the station ready to operate.
Other projects you may find relevant
All projectsarrow_forward
Holy Sites & HajjSupply, Installation & Operation of Waste Compactors at Kidana Al-Wadi Towers
View detailsarrow_forward
Holy Sites & HajjCompacting Bins & Stores in Mina
View detailsarrow_forward
Holy Sites & Hajj